<?xml version="1.0" encoding="UTF-8"?><rss version="2.0"
	xmlns:content="http://purl.org/rss/1.0/modules/content/"
	xmlns:wfw="http://wellformedweb.org/CommentAPI/"
	xmlns:dc="http://purl.org/dc/elements/1.1/"
	xmlns:atom="http://www.w3.org/2005/Atom"
	xmlns:sy="http://purl.org/rss/1.0/modules/syndication/"
	xmlns:slash="http://purl.org/rss/1.0/modules/slash/"
	>

<channel>
	<title>Lynn Canal Archives - KRBD</title>
	<atom:link href="https://www.krbd.org/tag/lynn-canal/feed/" rel="self" type="application/rss+xml" />
	<link>https://www.krbd.org/tag/lynn-canal/</link>
	<description>Community Radio for Southern Southeast Alaska</description>
	<lastBuildDate>Tue, 06 Jan 2015 19:31:00 +0000</lastBuildDate>
	<language>en-US</language>
	<sy:updatePeriod>
	hourly	</sy:updatePeriod>
	<sy:updateFrequency>
	1	</sy:updateFrequency>
	
	<item>
		<title>Despite spending freeze, Juneau road work continues</title>
		<link>https://www.krbd.org/2015/01/06/despite-spending-freeze-juneau-road-work-continues/</link>
					<comments>https://www.krbd.org/2015/01/06/despite-spending-freeze-juneau-road-work-continues/#respond</comments>
		
		<dc:creator><![CDATA[Ed Schoenfeld, CoastAlaska News]]></dc:creator>
		<pubDate>Tue, 06 Jan 2015 18:40:04 +0000</pubDate>
				<category><![CDATA[Local News]]></category>
		<category><![CDATA[Syndicated]]></category>
		<category><![CDATA[Alaska Committee]]></category>
		<category><![CDATA[Bill Walker]]></category>
		<category><![CDATA[Citizens Pro-Road]]></category>
		<category><![CDATA[Gov. Bill walker]]></category>
		<category><![CDATA[Juneau Access]]></category>
		<category><![CDATA[Juneau Access Road]]></category>
		<category><![CDATA[Lynn Canal]]></category>
		<category><![CDATA[SECC]]></category>
		<guid isPermaLink="false">http://www.krbd.org/?p=23778</guid>

					<description><![CDATA[<img width="480" height="360" src="https://www.krbd.org/wp-content/uploads/2015/01/6-19-13-End-of-road-direction-sign-at-Auke-Bay-ferry-terminal-e1420569140888.jpg" class="webfeedsFeaturedVisual wp-post-image" alt="" style="float: left; margin-right: 5px;" link_thumbnail="" decoding="async" fetchpriority="high" /><p>Work continues on Southeast Alaska's largest transportation project, despite Gov. Bill Walker’s spending freeze. </p>
<p>The post <a href="https://www.krbd.org/2015/01/06/despite-spending-freeze-juneau-road-work-continues/">Despite spending freeze, Juneau road work continues</a> appeared first on <a href="https://www.krbd.org">KRBD</a>.</p>
]]></description>
										<content:encoded><![CDATA[<img width="480" height="360" src="https://www.krbd.org/wp-content/uploads/2015/01/6-19-13-End-of-road-direction-sign-at-Auke-Bay-ferry-terminal-e1420569140888.jpg" class="webfeedsFeaturedVisual wp-post-image" alt="" style="float: left; margin-right: 5px;" link_thumbnail="" decoding="async" loading="lazy" /><div id="attachment_23780" style="width: 490px" class="wp-caption aligncenter"><a href="http://www.krbd.org/wp-content/uploads/2015/01/6-19-13-End-of-road-direction-sign-at-Auke-Bay-ferry-terminal-e1420569112280.jpg"><img loading="lazy" decoding="async" aria-describedby="caption-attachment-23780" class="size-full wp-image-23780" src="http://www.krbd.org/wp-content/uploads/2015/01/6-19-13-End-of-road-direction-sign-at-Auke-Bay-ferry-terminal-e1420569140888.jpg" alt="A sign near Juneau's Auke Bay Ferry Terminal points to the end of Glacier Highway. The road would be extended about 50 miles to a new terminal closer to Haines under a state plan that's temporarily on hold. (Ed Schoenfeld/CoastAlaska News)" width="480" height="360" /></a><p id="caption-attachment-23780" class="wp-caption-text">A sign near Juneau&#8217;s Auke Bay Ferry Terminal points to the end of Glacier Highway. The road would be extended about 50 miles to a new terminal closer to Haines under a state plan that&#8217;s temporarily on hold. (Ed Schoenfeld/CoastAlaska News)</p></div>
<p>Work continues on Southeast Alaska&#8217;s largest transportation project, despite Gov. Bill Walker’s spending freeze. But it doesn’t involve moving dirt or pouring concrete.</p>
<audio class="wp-audio-shortcode" id="audio-23778-1" preload="none" style="width: 100%;" controls="controls"><source type="audio/mpeg" src="http://www.krbd.org/wp-content/uploads/2015/01/05RoadStop-L.mp3?_=1" /><a href="http://www.krbd.org/wp-content/uploads/2015/01/05RoadStop-L.mp3">http://www.krbd.org/wp-content/uploads/2015/01/05RoadStop-L.mp3</a></audio>
<div id="attachment_23782" style="width: 330px" class="wp-caption alignright"><a href="http://www.krbd.org/wp-content/uploads/2015/01/24JuneauAccessMap-e1420569419633.jpg"><img loading="lazy" decoding="async" aria-describedby="caption-attachment-23782" class="size-full wp-image-23782" src="http://www.krbd.org/wp-content/uploads/2015/01/24JuneauAccessMap-e1420569419633.jpg" alt="DOT's preferred alternative would extend Glacier Highway about 50 miles to a ferry terminal at the Katzehin River. (Courtesy Alaska Department of Transportation and Public Facilities)" width="320" height="436" /></a><p id="caption-attachment-23782" class="wp-caption-text">DOT&#8217;s preferred alternative would extend Glacier Highway about 50 miles to a ferry terminal at the Katzehin River. (Courtesy Alaska Department of Transportation and Public Facilities)</p></div>
<p>The <a href="http://dot.alaska.gov/sereg/projects/juneau_access/index.shtml" target="_blank">Juneau Access Road</a> is one of six projects Walker <a href="http://gov.alaska.gov/Walker/press-room/full-press-release.html?pr=7050" target="_blank">put on hold</a> during his first month in office.</p>
<p>It would extend the capital city’s highway system about 50 miles north to a new ferry terminal on Lynn Canal. From there, <a href="http://www.krbd.org/2014/12/15/keel-laying-marks-start-of-ferry-construction/" target="_blank">shuttle ships</a> would complete the link to Haines and Skagway.</p>
<p>In his announcement, Walker told state agencies they could complete what’s already paid or contracted for. But he said no additional money could be committed or spent.</p>
<p>Juneau Access Project Manager Gary Hogins says the Department of Transportation’s current work is preparing a <a href="http://dot.alaska.gov/sereg/projects/juneau_access/documents.shtml" target="_blank">Draft Supplemental Environmental Impact Statement</a>, which is needed for federal funding and approval.</p>
<p>&#8220;We just finished going through the public involvement process and what we do next is review the comments, respond to comments and evaluate and select a final alternative,&#8221; he says.</p>
<p>Hogins says that will take about a year and $600,000.</p>
<p>He says no other work is planned – for now.</p>
<p>&#8220;We would have expected to go into design and construction, but that’s been put on hold,&#8221; he says.</p>
<p>&#8220;Gov. Walker has made a very smart decision to put the brakes on the Juneau Road extension,&#8221; says Emily Ferry of the <a href="http://seacc.org/transportation/juneau-road" target="_blank">Southeast Alaska Conservation Council</a>.</p>
<p>SEACC says the Alaska Marine Highway System offers a safer, more environmentally friendly alternative.</p>
<p>&#8220;DOT’s own study shows the extraordinary cost of constructing and maintaining the road far exceeds the minimal benefits of making weekend getaways a little bit cheaper for Juneauites,&#8221; she says.</p>
<p>The agency says the road would do a lot more than that. It also says the project would ultimately save money by shortening ferry routes.</p>
<p><a href="http://cpralaska.com/" target="_blank">Road supporters</a>, who share those views, say they’re not giving up.</p>
<blockquote><p>&#8220;I’m disappointed in it. I don’t know that that’s the end of the project. I think it’s a bump, probably for all those other projects too. I think they’ll probably all come back at some point in time,&#8221; says Wayne Jensen, who chairs the <a href="http://www.alaskacommittee.com/Default.aspx" target="_blank">Alaska Committee</a>’s board of directors.</p></blockquote>
<p>He supports building the road to increase access to the capital city. He remains optimistic.</p>
<p>&#8220;The stuff that’s committed is continuing and I think that’s a good sign. They’ve got contracts committed and processes in play. And I expect those will continue until some point in time when either there’s a further delay or the projects are reinstated,&#8221; he says.</p>
<p>The Transportation Department recently increased road funding in its long-term project list, called the <a href="http://www.dot.state.ak.us/stwdplng/cip/stip/assets/STIP.pdf" target="_blank">Statewide Transportation Improvement Program</a>.</p>
<p>The proposed $152 million brings the total to be spent to $520 million.</p>
<p>Road projects of a similar value in Anchorage, Wasilla, Cordova and the eastern Interior were removed from the list.</p>
<p>SEACC’s Ferry says that’s wrong.</p>
<blockquote><p>&#8220;If DOT is allowed to proceed with the Juneau Road extension, other transportation projects across the state will have to be sacrificed over the next decade,&#8221; she says.</p></blockquote>
<p>It’s not clear when the governor will decide what to do with the Juneau Access project.</p>
<p>DOT’s Hogins says he’s assembling the data.</p>
<p>&#8220;He’s asked for information as far as what would be the downside or the risk of delay or termination. And we are responding to that,&#8221; he says.</p>
<p>Walker said low oil prices mean the state cannot afford the road &#8212; and <a href="http://www.ktoo.org/2014/12/27/walker-halts-progress-juneau-access-5-megaprojects/" target="_blank">the other five projects</a> &#8212; right now. The state faces an approximately $3 billion budget gap for the current fiscal year and the same for the next one.</p>
<p>Other projects put on hold are the Ambler Road, the Susitna-Watana Dam, the Kodiak Launch Complex, the Knik Arm Crossing and the Alaska Standalone Pipeline Project.</p>
<p>The post <a href="https://www.krbd.org/2015/01/06/despite-spending-freeze-juneau-road-work-continues/">Despite spending freeze, Juneau road work continues</a> appeared first on <a href="https://www.krbd.org">KRBD</a>.</p>
]]></content:encoded>
					
					<wfw:commentRss>https://www.krbd.org/2015/01/06/despite-spending-freeze-juneau-road-work-continues/feed/</wfw:commentRss>
			<slash:comments>0</slash:comments>
		
		<enclosure url="http://www.krbd.org/wp-content/uploads/2015/01/05RoadStop-L.mp3" length="3598214" type="audio/mpeg" />

			</item>
		<item>
		<title>Latest shuttle ferry plan closes car deck</title>
		<link>https://www.krbd.org/2013/07/15/latest-shuttle-ferry-plan-closes-car-deck/</link>
					<comments>https://www.krbd.org/2013/07/15/latest-shuttle-ferry-plan-closes-car-deck/#respond</comments>
		
		<dc:creator><![CDATA[Ed Schoenfeld, CoastAlaska News]]></dc:creator>
		<pubDate>Tue, 16 Jul 2013 05:11:52 +0000</pubDate>
				<category><![CDATA[Local News]]></category>
		<category><![CDATA[Syndicated]]></category>
		<category><![CDATA[Alaska Class Ferry]]></category>
		<category><![CDATA[Alaska Class Shuttle Ferries]]></category>
		<category><![CDATA[Lynn Canal]]></category>
		<guid isPermaLink="false">http://www.krbd.org/?p=12704</guid>

					<description><![CDATA[<img width="530" height="281" src="https://www.krbd.org/wp-content/uploads/2013/07/7-15-13-Shuttle-ferry-drawing-EBD-DayBoatACF-PrelimDesignStudyReport-page-45-e1373950896845.jpg" class="webfeedsFeaturedVisual wp-post-image" alt="" style="float: left; margin-right: 5px;" link_thumbnail="" decoding="async" loading="lazy" /><p>The latest design for new shuttle ferries includes a covered car deck. But it doesn’t address some other concerns, such as minimal food service.</p>
<p>The post <a href="https://www.krbd.org/2013/07/15/latest-shuttle-ferry-plan-closes-car-deck/">Latest shuttle ferry plan closes car deck</a> appeared first on <a href="https://www.krbd.org">KRBD</a>.</p>
]]></description>
										<content:encoded><![CDATA[<img width="530" height="281" src="https://www.krbd.org/wp-content/uploads/2013/07/7-15-13-Shuttle-ferry-drawing-EBD-DayBoatACF-PrelimDesignStudyReport-page-45-e1373950896845.jpg" class="webfeedsFeaturedVisual wp-post-image" alt="" style="float: left; margin-right: 5px;" link_thumbnail="" decoding="async" loading="lazy" /><div id="attachment_12706" style="width: 540px" class="wp-caption aligncenter"><a href="http://www.krbd.org/wp-content/uploads/2013/07/7-15-13-Shuttle-ferry-drawing-EBD-DayBoatACF-PrelimDesignStudyReport-page-45.jpg"><img loading="lazy" decoding="async" aria-describedby="caption-attachment-12706" class="size-full wp-image-12706" title="7-15-13 Shuttle ferry drawing EBD DayBoatACF-PrelimDesignStudyReport-page-45" src="http://www.krbd.org/wp-content/uploads/2013/07/7-15-13-Shuttle-ferry-drawing-EBD-DayBoatACF-PrelimDesignStudyReport-page-45-e1373950896845.jpg" alt="" width="530" height="281" /></a><p id="caption-attachment-12706" class="wp-caption-text">A drawing of the Alaska Class Shuttle Ferry by Elliot Bay Design. A new report estimates building two will cost $112.2 million. They will likely be built at the Ketchikan shipyard and will sail Lynn Canal.</p></div>
<audio class="wp-audio-shortcode" id="audio-12704-2" preload="none" style="width: 100%;" controls="controls"><source type="audio/mpeg" src="http://www.krbd.org/wp-content/uploads/2013/07/15DesignPkg-L.mp3?_=2" /><a href="http://www.krbd.org/wp-content/uploads/2013/07/15DesignPkg-L.mp3">http://www.krbd.org/wp-content/uploads/2013/07/15DesignPkg-L.mp3</a></audio>
<p>The latest design for new shuttle ferries includes a covered car deck. But it doesn’t address some other concerns, such as minimal food service.</p>
<p>What’s called a <a href="http://dot.state.ak.us/amhs/alaska_class/documents/DayBoatACF-PrelimDesignStudyReport.pdf" target="_blank">design study report</a> for the Alaska Class Shuttle Ferries was released Monday. Two ships are planned for Juneau, Haines and Skagway sailings.</p>
<p>Alaska Marine Highway spokesman Jeremy Woodrow says the report calls for a fully enclosed car deck. Earlier plans left the rear part open.</p>
<p>&#8220;The point of shielding the car deck from extreme weather really isn’t the main reason behind it. More of a reason is that the additional costs really wouldn’t be that much to the point where it would be worthwhile leaving it open,&#8221; Woodrow says.</p>
<p>Longtime passengers and community leaders objected to an open deck, saying salt spray and ice would damage vehicles.</p>
<p>Skagway tugboat captain Mike Korsmo serves on the state’s Marine Transportation Advisory Board. He likes the change.</p>
<p>&#8220;That’s a good thing. I think that was kind of a clear message that they got, that people didn’t want to see an open car deck,&#8221; Korsmo says.</p>
<p>Size and capacity requirements have not changed much since the last proposal.</p>
<p>Shuttle ferries would be 280 feet long, larger than the small ferry LeConte, which sails the route part of the year.</p>
<p>They will have indoor seating for 300 passengers and parking for about 50 cars and trucks.</p>
<p>A larger ferry design discarded late last year called for several small quiet rooms for families, the sick, or the elderly.</p>
<p>That’s been dropped. But Woodrow says some options remain.</p>
<p>&#8220;There’s going to be a theater lounge as well as a children’s area, a family area. And then there’s going to be what’s called a library or a quiet room as well that kind of acts as &#8230; the observation lounge, which tends to be a quieter area,&#8221; Woodrow says.</p>
<p>Plans continue to call for a small food court and vending machines.</p>
<p>Korsmo understands the need to save money, but says passengers will miss having a full kitchen.</p>
<p>&#8220;I took pictures this winter of the lineups on the LeConte of people waiting for food. So I’m sure it’s going to be somewhat of a letdown to the traveling public, especially in the wintertime,&#8221; Korsmo says.</p>
<div id="attachment_8785" style="width: 310px" class="wp-caption alignright"><a href="http://www.krbd.org/wp-content/uploads/2012/12/Alaska-Class-Ferry-drawing-eliott-bay-design1-e1356115300204.jpg"><img loading="lazy" decoding="async" aria-describedby="caption-attachment-8785" class="size-medium wp-image-8785" title="Alaska Class Ferry drawing eliott-bay-design" src="http://www.krbd.org/wp-content/uploads/2012/12/Alaska-Class-Ferry-drawing-eliott-bay-design1-300x101.jpg" alt="" width="300" height="101" /></a><p id="caption-attachment-8785" class="wp-caption-text">A drawing of the earlier, larger proposed Alaska Class Ferry from Elliott Bay Design Group.</p></div>
<p>The ships are designed to sail 12-hour days, not overnight. The design will include bow and stern doors to allow faster roll-on, roll-off loading and unloading. Side doors will allow docking at more terminals.</p>
<p>The latest cost estimate is $112.2 million for both ferries. That’s $5 million more than the previous figure, but still below the $117 million allocated by the Legislature.<br />
In addition to Lynn Canal, the shuttle ships could sail to northern Southeast villages or Prince William Sound communities.</p>
<p><a href="http://www.dot.state.ak.us/amhs/alaska_class/submit_comment.shtml" target="_blank">Public hearings</a> are planned for August 20th, 21st and 22nd in Juneau, Skagway and Haines.</p>
<p>The post <a href="https://www.krbd.org/2013/07/15/latest-shuttle-ferry-plan-closes-car-deck/">Latest shuttle ferry plan closes car deck</a> appeared first on <a href="https://www.krbd.org">KRBD</a>.</p>
]]></content:encoded>
					
					<wfw:commentRss>https://www.krbd.org/2013/07/15/latest-shuttle-ferry-plan-closes-car-deck/feed/</wfw:commentRss>
			<slash:comments>0</slash:comments>
		
		<enclosure url="http://www.krbd.org/wp-content/uploads/2013/07/15DesignPkg-L.mp3" length="3966018" type="audio/mpeg" />

			</item>
	</channel>
</rss>

<!--
Performance optimized by W3 Total Cache. Learn more: https://www.boldgrid.com/w3-total-cache/?utm_source=w3tc&utm_medium=footer_comment&utm_campaign=free_plugin

Page Caching using Disk: Enhanced 
Minified using Disk

Served from: www.krbd.org @ 2026-09-21 07:03:35 by W3 Total Cache
-->